claudeClaude Emond is one of the founders and president of Qualiscope Enterprises, a project management consulting, coaching and training firm based in Montreal, Canada. He has degrees in chemical engineering from Canada's Royal Military College (BEng) and Montreal McGill University (MEng), a MBA from Ottawa University, workshop leadership training from Le Centre Quebecois de la PNL, and is a certified PMP. He has over 25 years experience managing major public and private projects. He teaches project risk management in the Schulich School of Business Master certificate in project management and the PMP certification revision class for PMI, Montreal He is one of the authors of the current PMI Standards for Portfolio Management. Claude can be reached at claude.emond@qualiscope.ca.

The Rules of Lean Project Management: Part 6

Opening, Adapting and Closing Often

I continue here to expand my set of “rules” of Lean PM, following Hal Macomber’s comments on my original four rules series in his blog (http://www.reformingprojectmanagement.com/2008/11/09/883/).

Another lean principle Hal said I had left out was the necessity to PDCA everything (the Deming Wheel - http://en.wikipedia.org/wiki/Shewhart_cycle). Hal notices in his blog that “much has been made of the tools, techniques and methods of lean ways of working. But behind it all is Deming's (Shewhart's) Plan - Do - Check - Adjust cycle. It's the embodiment of the scientific method. No company does it better than Toyota. Make it your habit.” Hal has however revisited the PDCA acronym by replacing the original meaning of the “A” (Act) by Adjust. And I will also revisit, because I believe the PDCA cycle, as stated, does not clearly illustrate what should be project work.

In the current edition of the PMBoK (3rd ed., 2004), PMI also acknowledges the importance of the PDCA cycle in project management, but goes on promoting its own version of it, the IPECC cycle (Initiate, Plan, Execute, Control and Close). There are slight but significant differences between those two cycles, differences that mirror those between recurrent operations and projects:

  • PMI “I” (Initiate) is inherent to projects (they start somewhere), hence not included in the more generic PDCA cycle
  • PMI “P” (Plan) is similar to Deming “P” (Plan)
  • PMI “E” (execute) is similar to Deming “D” (do)
  • PMI first “C” (Control) is equivalent to some extent to Deming “CA” (Check, Act). Continuous improvement in project management requires a special kind of acting to handle major project uncertainties and inherent changes. So for projects, Adapt would be a better word than Act and, I believe, more representative of high-uncertainty projects reality than the word Adjust
  • PMI second “C” (Close) is also inherent to projects (they have to close, while we do not want to close operational business processes), hence also not included in the more generic PDCA cycle. Granted, one could argue that Acting in the case of a project includes Closing it.

Hal said that we had to “PDCA everything.” The word everything is, for me, the key to the Lean PM philosophy and is related to LPM rule No. 2 (Track small concrete promises that you can see evolving over time). Everything, for me, means: each activity, each deliverable (daily and weekly promises/deliverables if you think Lean or Agile PM), each work package, each phase/stage of the project as they evolve.

So I submit that, for projects, we have to IPDCAdC continuously. Initiate, Plan, Do, Check, Adapt and Close everything. Open-Adapt-Close often. Open new work, adapt to change as you do it, and close it to the satisfaction of all stakeholders. And one must not forget that some projects need to be terminated before they are completed, if they cannot deliver what is required; so Close can also mean Stop!

In acknowledgement of Hal’s revisited comment, here’s Rule number 6 of 8 of Lean Project Management: The Open-Adapt-Close Often rule.

Rule No. 6 of LPM. Open-Adapt-Close, Open-Adapt-Close, Open-Adapt-Close… all the time.
The IPECC cycle is a recurring process; this recurrence is the true key to successful projects, lean-influenced or not. In order to close a project, you have to open-adapt-close formally at the phase level, to open-adapt-close formally at the work package level, to open-adapt-close for each required deliverable (small concrete promises), to open-adapt-close each required activity undertaken.

Hits: 1216
Comments (2)Add Comment
Qingyu Wang
...
written by qingyu, January 14, 2009
I would like to relate this PDCA model further to Quality Management, which is an integral part of Project Management. "C - Check" means Quality Control, Quality Assurance and Quality Audit activities to me, and "A - Adjust/Act" means Corrective Actions and the spirit of Continual Improvement. This could also be applied to the day to day activities such as supervising children to deliver a quality homework.
Claude Emond
...
written by claudeemond, January 14, 2009
I agree 100% with you. PDCA has to do with continuous improvement and comes from the quality management world, mostly for recurring processes.

I give PMP Certification preparation classes for PMIMontreal and I cover the Quality Management Knowledge Area. PMBoK says the quality of a project is the quality of its products (end deliverables - the planned destination)PLUS the quality of the management of the project (the journey through change itself. The current PMBoK says a lot about quality of the product and talks about process flow charts, pareto law, random sampling techniques, etc.. interesting stuff but stuff that concerns more the world of recurrent production. It falls short of covering the quality of the journey (let's see the coming 5th edition if it has improved); PMBoK says a lot about the planning of this journey but very little yet on its execution, including «change management» as the project AND its environment evolve, which is not the same as «managing scope or other project changes».

So what I try to say here in my blog is that the usual PDCA cycle, discussed in the literature and quality circles, relates to the end deliverables of the project and that IPECC is a special-case PDCA for temporary non-recurring activities, i.e. a project and its journey from start to finish.

When Hal Macomber said we should PDCA everything, I am quite sure (we have been discussing those things for many years Hal and me)he means by this «everything», not only product oriented work (technical transaction-driven stuff) but also project management oriented work (the psychological, perceptual, relationship-driven stuff that happens during the project, the journey through change). This relationship-driven stuff is «PDCAed» using «IPECC», not normal process improvement «PDCA»..and «IPECCing» very, very often (on «everything»). Hope this clarifies the 6th rule of LPM.

Write comment
You must be logged in to post a comment. Please register if you do not have an account yet.
Click Here to login or create a free account.

busy