From the Sponsor's Desk - The Power of Teams

Written by 
Rate this item
(0 votes)
In my last post, Speaking Truth to Power, I reviewed a project that was rescued by a PM that had the courage of his convictions. I also looked at how this Great PM leveraged the Project Pre-Check fundamentals of stakeholders, defined processes and a best practice based decision framework to achieve great results.

In this post, we’ll look at a project that succeeded because the PM went that extra mile to build a great team. That’s why I call this post The Power of Teams!

The Situation

 This organization was a large financial services firm with a large, highly productive sales organization. Over time, with the introduction of new products and services and changes in the competitive marketplace, the sales compensation and recognition programs became less focused and did not always promote behaviours that were in the best interests of the clients and the company.

The Goal

The Vice President of Sales, the sponsor of the venture, announced that a major reworking of the sales compensation and recognition programs was necessary to meet the ongoing and future needs of clients and the company. The new programs were to be introduced effective January 1, fourteen months in the future.

The Project

With only fourteen months to get the job done, the CIO recognized the risk. Prior experience with sales compensation and recognition changes suggested this instance would be in the $5 million range and require more than fifty project staff at the peak. To compound the challenge, there was a corporate system freeze on anything but critical changes which started six weeks before year end.

While the general direction of the compensation changes had been set, the details had yet to be determined. Consequently, a PM was selected who had a great track record with ill defined projects and superb leadership and communication skills. The PM focused on building his IT core team according to the following criteria:

  • The ability to contribute effectively at any stage of the project, from business conceptualization to post implementation support.
  • Proven expertise in all of the technology platforms, development practices and tools involved.
  • Great team and communication skills up, down and sideways.
  • Fast learner and self starter with excellent time management skills.

Fortunately, the organization had an effective Portfolio Management process in place and the compensation changes were given a high priority, at the top of the food chain when it came to acquiring resources. That made it relatively easy for the PM to hand-pick the right staff from across the organization, in spite of more than a few grumbles from other sponsors and PMs. Of course, the staff assigned to the project realized the prestige of being selected and that provided a powerful catalyst to help the team jell and excel. 

Within a month, the PM had assembled his core group of twenty IT staff. He recognized that the project’s success depended on the ability of that group to far exceed the sum of the parts and so he set about shaping those twenty individuals into a high performance team.

The Result

The project implemented successfully just prior to the year end freeze, twelve and a half months after launch. The actual cost was slightly under budget and the quality of the delivered software, processes and services was outstanding.

In fact, the sponsor, who was known for staging extravagant sales conferences and ignoring the achievements of his head office organization, reserved a local, high end restaurant to wine and dine all the project staff, business and IT, as well as their spouses, over 160 people in total. Each team member received an engraved pen and pencil set. Each spouse received a set of engraved wine goblets. When was the last time a sponsor on one of your projects took you out to a high end restaurant and bought you personalized gifts?    

How this Great PM Helped

This project had one significant advantage; the vast majority of those affected by the planned changes reported to the sponsor. The PM leveraged that reality to get the attention of the managers affected and the right business staff assigned. In addition, the PM focused on the following areas to deliver a successful result:

  • He built the capability of his IT team and the overall business/IT group with frequent sponsor encounters stressing the common mission, vision, goals and priorities.
  • He ensured at least one of his core team members was involved with each business area from the start to assess alternatives and develop the final specifications.
  • He developed and vetted team ground rules re operation, communication, confidentiality, sign-off’s, etc.
  • He gave the core team the ability to recruit and add additional IT resources as the need became apparent, and to move team members out if they weren’t cutting it.
  • He allowed the core team to set their own schedules, work hours, days off, vacations and found that they were more demanding of themselves than he would have ever been.
  • He developed and managed a comprehensive risk plan to reduce or eliminate high impact and high probability risks.
  • He refined the existing software development methodology to ensure the quality of each deliverable and reduce the time required for rework.

If you find yourself on a similar project, put these points on your checklist of things to do so you too can be a great PM. And your sponsor’s best friend!

Next time, we’ll look at a situation that happens all too often – assigning someone to manage a key project who has no prior PM experience, no formal PM education and no in place mentor. In the interim, if you have a project experience, either good or bad, past or present, that you’d like to have examined through the Project Pre-Check lens, send me the details and we’ll have a go.

 Don’t forget to leave your comments below


Read 1038 times Last modified on Wednesday, 29 September 2010 15:54
Drew Davison

Drew Davison is a former IT practitioner, project manager and system development executive, the owner and principal consultant at Davison Consulting, a senior consultant at The Manta Group and the author of Project Pre-Check: The Stakeholder Practice for Successful Business and Technology Change. He works with organizations that are planning or undergoing major business and technology change to access the power of the Project Pre-Check building blocks; an effective stakeholder group, defined and proven processes and the decision framework, a mechanism for quickly leveraging industry best practices. Drew can be contacted directly at drew.davison@mantagroup.com