Wednesday, 12 August 2009 10:36

Projects without Borders; Gathering Requirements on a Multi-Cultural Project

Written by

Co-authored by Richard Larson

One of the most difficult tasks project managers and business analysts face is obtaining customer requirements. Even when business customers and the business analyst work in the same building, misunderstandings are bound to arise. And as more and more businesses expand beyond their borders, different terminology and ways of doing things the risk of things going awry gets even greater. It's a challenge to ask the right questions, get the right people involved, and document unambiguous requirements, regardless of the backgrounds of those participating. When the project includes multi-cultural stakeholders, particularly if they comprise a virtual team working in geographically dispersed areas, often thousands of miles, time zones and oceans apart, the job becomes much harder.

Some of the challenges facing project managers and business analysts are not unique to multi-cultural projects. However, personal agendas, conflicts about roles and priorities, and availability worsen the situation. In addition, recent studies have shown that almost half of the typical project budget is spent reworking requirements defects. While there are many underlying reasons for this rework, dealing with a group of multi-cultural business customers and/or project team members can create significant hurdles.

The Challenges

Physical Distance of Stakeholders

Although many of the challenges exist even when the team and business customers are located on the same floor in the same building, the difficulties in dealing with them increase with physical distance. Time zones make meetings hard to schedule. Business analysts on today's global projects have learned that the standard eight-hour work day doesn't exist. If we are truly customer-focused and interested in building relationships to capture requirements, we schedule meetings at a time convenient to our customers, not to us.

Few meetings on global projects are face-to-face, making the assessment of non-verbal communication nearly impossible. Since most business analysts pay a great deal of attention to non-verbals as part of the elicitation process, not being able to see them diminishes the communication and therefore the ability to capture requirements. Finally, although there are alternatives to face-to-face meetings, neither video conferencing nor "net" meetings is ideal. Video conferences usually lack some spontaneity and the audio lag can be distracting. Facilitating large groups over a video conference is quite challenging, since multiple conversations, dominance of one group or individual, and other facilitation difficulties abound. With both video-conferencing and net meetings, there are often equipment issues which hinder the requirements elicitation.

Roles and Responsibilities

Unclear roles and responsibilities can be the bane of project mangers and business analysts everywhere. When they are unclear, tasks invariably fall through the cracks and finger-pointing ensues. Unfortunately when stakeholders are removed from each other, it takes longer to find omissions and the resulting errors are harder to correct. Trouble usually occurs if a business analyst expects the business client to define the requirements, but the business client thinks they have already provided the solution and the rest is up to the business analyst. With differing cultural attitudes towards conflict, it can take even longer to perceive that there is a difference of opinion, let alone resolve it.

Language

Language barriers across cultures are numerous. The difficulties caused by differences in languages and even pronunciation among the stakeholders is well-known. In addition, most people have different levels of understanding and expressing both written and oral languages that are not in their tongue. For example, some people can understand another language when spoken, but have difficulty writing it. Others can understand better than they speak and write better than they understand. In order to elicit the requirements, project managers and business analysts need to work with business customers whose language differs from theirs to assess the comfort with both written and oral communications.

Finally, we need to consider the use of TLAs (three-letter acronyms), humor, euphemisms (powder room, passed away, downsizing), and sports analogies (ballpark estimate, coming out of left field, long shot) that can cause confusion and misunderstanding.

The Cultural Landscape

Another barrier is assuming that all team members, whether or not they are collocated, approach the project with the same cultural perspective. For example, I was managing a project that included a male team member who appeared uncomfortable taking direction from a woman. The more I discussed the importance of meeting deadlines, communicating status, and teamwork, the more uncommunicative and uncooperative he became. Finally I realized that the real problem was that I had done nothing to build trust and a strong relationship with him. His cultural work ethic dictated the importance of relationships. Therefore, he completed tasks because of the relationship, not because tasks appeared on a work breakdown structure.

Tips and Techniques for Making it Work

As organizations take on more global projects or projects that include a diverse set of business customers, they need to establish a corporate mindset of acceptance, inclusion, and learning that crosses borders. In addition, the project team needs to understand its inter-dependency in order to have project success. Synergy between the business customers and the project manager or business analyst is required to ensure that the end product is successful. Therefore, each party, the project manager, business analyst, sponsor, and all the business customers have an obligation and a stake in making this cultural diversity work. Without the project manager, the organization will spend more time and money on failed projects. Without the business analyst, the end product will not be usable. Without strong sponsorship and actively engaged business clients, the true requirements will not be discovered, and the end product will not be viable.

Although each party has its responsibility for making the project and end product successful, there are some things that the project manager and business analyst can do that help bridge the cultural gap.

Build Relationships and Trust

Building relationships and trust is important on all projects. There are a myriad of ways business customers can sabotage a project if they are afraid that the end result will jeopardize or dramatically change their jobs, or when the local requirements are not taken into account. With good relationships, issues surface more easily and can be resolved quicker.

The different requirements elicitation venues promote team-building to a greater or lesser degree.

  • For example, the use of surveys does little to promote mutual understanding.
  • Facilitated sessions (which may have to be net meetings on global projects) can help build teamwork, but it could take weeks or months for a virtual team to solidify.
  • One-on-ones serve to build relationships and help navigate the political and cultural landscape. By meeting individually, the project manager or business analyst can assess commitment to the project, discuss individual concerns, gather requirements from those who may not speak up in meetings, and gather requirements related to local needs of the global business experts. One-on-ones can also more easily promote understanding of team members from various cultural backgrounds, because language differences are the least problematic and personal stories and experiences can be more easily shared.

Define Roles and Responsibilities Using a Matrix

One technique that can aid in avoiding the pitfalls of unclear roles and responsibilities is to document them using some form of matrix, such as the Responsibility Assignment Matrix or the RACI chart. These tools use minimal text, so they are easier to understand than textual descriptions. In addition, in order to complete them, valuable discussion needs to occur. By facilitating this discussion, the project manager can help ensure that the fine distinctions between such things as a role and responsibility can be cleared up earlier rather than later in the project.

Example RACI Chart

(Responsibility for doing the work, Accountability for decisions, Consult with on the work, Inform that the work has completed)

Task/Phase

R

A

C

I

Project Plan Martha Mary PMO Team
Requirements List Martha Client Requirements Consultant Team
Client's Staff
Modeling (Process, Use Case, and Data) Ying, Susan, David Mary DBA Team
User Interface Requirements/Prototyping Martha, David Mary Usability Lab Team
Programming Sunil, Shashi Mary All BAs Team
User Acceptance Testing Martha Client Sunil, Shashi

Model the Requirements

One of the best ways to elicit requirements is to use various models to represent the requirements. Models, such as process models, usage models, and prototypes can provide a structure that encourages asking questions to find hidden requirements and more quickly document a complete set of requirements. Models have a number of advantages in general, and for cross-cultural projects in particular:

  • Models have the advantage of needing few words, so the language issues can be more easily overcome. They also have the advantage of promoting a two-way translation of requirements, from business customer to the model and back to the business customer, again with a great deal of structure and a minimum use of words. Models should be created so that they are clear and for the most part understood and used by the business clients.
  • Models are the most effective way to avoid having different members of the group have different mental pictures of the requirements. They are, for the most part, culturally independent. They can be created using several of the requirements venues including facilitated sessions, one-on-ones, and observation.
  • Models can help traverse the cultural landscape because they produce unambiguous requirements. That is, there is little room for misinterpreting them. Regardless of the birth countries of the business customers, business analyst, and team, cultural interpretations of the requirements are minimized by using pictures instead of text.
  • Finally models can be used whether or not the business customers are local or dispersed. Technology now permits models to be easily shared in-person, by email, with video-conferencing, and with net meetings. Because models can be viewed by all, there is less chance for miscommunication of requirements.

Summary

A large, multi-national U.S.-based pharmaceutical client of ours regularly experiences the challenge of cross-cultural requirements gathering. The following are some anecdotes to summarize a few of the key points in this article.

  • A conference call with a Tokyo client took twice as long to review a process flow as with domestic clients. The analyst kept asking "is there anything else" because of not wanting to omit something important. (Conclusion: plan for extra time when working cross-culturally.)
  • A similar group of Japanese clients insist on spending time at the beginning of a project getting to know their IT counterparts. They frequently and repeatedly ask that the IT staff come over to Japan to meet and visit with them. When the groups do meet in person, each meeting ends with a glass of sake to celebrate. (Conclusion: relationships are more important than the work in some cultures than others, even to the extent of delaying work. Projects will be stalled until relationships are established, and trust may be even more difficult to establish.)
  • A cross-cultural team of American, French, and British clients spent two hours talking about an industry term that the three groups swore had three different meanings. They later discovered the terms were really the same and then had to agree on which one to adopt. (Conclusion: language differences will be a challenge, so take the time to define key terms and record them in a glossary during projects.).
  • A project manager made an onsite visit to a client from Latin America on a project. The project manager had written in an email that he had found a restaurant to go to, but you had to BYOB. The client was confused and asked when they got together: "who is 'bee-yob'?" (Conclusion: be careful with and define all acronyms!)

In sum, gathering requirements on a multi-cultural project has numerous challenges. To avoid or lessen the affects of these pitfalls, project managers and business analysts should spend time developing relationships, clarify roles and responsibilities in a chart format to ensure understanding by all, use terms and language carefully, and model the requirements to help ask questions. The ultimate goal is to uncover requirements in a way that is easier for all stakeholders, regardless of their language and culture.

Don't forget to leave your comments below


Elizabeth Larson, CBAP, PMP, and Richard Larson, CBAP, PMP, are Co-Principals of Watermark Learning (www.watermarklearning.com), a globally recognized business analysis and project management training company. Over 20 years, they have used their extensive experience in both business analysis and project management to help thousands of BA and PM practitioners develop new skills. They have helped build Watermark's training into a unique combination of industry best practices, an engaging format, and a practical approach. Attendees immediately learn the retainable real-world skills necessary to produce enduring results. Between them they have presented workshops, seminars, and training classes on three different continents to over 15,000 attendees. Their speaking history includes repeat appearances at Project Management Institute (PMI®) North American, European, and Asia-Pacific Congresses, and at Business Analyst World conferences around North America. Both Elizabeth and Richard are among the world's first Certified Business Analysis Professionals (CBAP®) through the International Institute of Business Analysis (IIBA®) and are contributors to the IIBA Business Analysis Body of Knowledge (BABOK®). They are also certified Project Management Professionals (PMP®) and are contributors of the section on collecting requirements in the upcoming 4th edition of the Project Management Body of Knowledge (PMBOK®).

Read 8457 times
Elizabeth Larson

Elizabeth Larson, PMP, CBAP, CSM, PMI-PBA is Co-Principal and CEO of Watermark Learning and has over 30 years of experience in project management and business analysis. Elizabeth’s speaking history includes repeat presentations for national and international conferences on five continents.

Elizabeth has co-authored five books on business analysis and certification preparation. She has also co-authored chapters published in four separate books. Elizabeth was a lead author on several standards including the PMBOK® Guide, BABOK® Guide, and PMI’s Business Analysis for Practitioners – A Practice Guide.

© ProjectTimes.com 2019

macgregor logo white web