Wednesday, 29 August 2012 09:42

The Problem with Red, Yellow, Green Project Status

Written by 
Rate this item
(5 votes)

Many years ago I worked in a Project Management Office at a large financial institution. Once a week I prepared a project status report for executive management and the PMO director. I would calculate how we were tracking to budget, list any major issues or risks, and summarize overall status.

GregAug291

I was also told to mark the project as red, yellow, or green – using the following definitions:

Red: Serious issues and the project will probably be delayed or have significant budget overrun.
Yellow: Potential issues with schedule or budget, but both can probably be saved with corrective actions.
Green: On schedule, on budget, all good.

The red/yellow/green approach seems simple and logical. You only worry stakeholders if something goes wrong, so green projects do not need much review or attention.

However, in my experience the color approach has many shortcomings and potential repercussions. Let’s look at few.

Expectations

What happens when a green project turns yellow or red? In my experience there is an emotional conversation with stakeholders. Here are some of comments I frequently hear when a project goes from green to yellow:

“What went wrong?”, “Why didn’t you manage this project better?, “How can we avoid this happening again?”, “Why didn’t you see this coming?”.

As a project manager I often feel great guilt with these conversations and I too question my competency. But if we spend a moment and work our way through the guilt and emotion, we can see this issue from a more analytical perspective.

Not in line with normal project uncertainty

You may be familiar with the cone of uncertainty. The cone of uncertainty tells us that you cannot completely understand all of the tasks and potential issues within a project, at the beginning of a project.

GregAug292

As the project progresses we learn more and there are less risks,  but we can never anticipate everything that could go wrong until the project is 100% complete.
When we label a project as green we are telling the sponsor everything is OK, today.

Sponsors interpret green as everything is OK today and it should be for the entire project. It is human nature to assume the project is under control and should stay under control.

A Different Approach

But since any experienced project manager knows that green does not necessarily mean green forever, we need to speak in verbiage that stakeholders can relate to. To address this issue I have changed my color scheme when working with sponsors and removed green from my status options.

My options are now:

Yellow: The project does not have any known issues but there is still high risk that something could go wrong (as demonstrated by the cone of uncertainty). As with any project in flight, we are managing it cautiously and we are doing our best to deliver successfully.

Orange: An issue has surfaced and the project goals are in jeopardy. We are triaging the issue(s) and at this time we believe we can still be successful
Red: An issue has surfaced and we do not believe 100% project success can be obtained due to the discovery. More than likely we will either miss the desired date, or exceed budget, or not be able to deliver the desired scope by the target date.

Conclusion

What do you think of my approach? I welcome your thoughts. I know many stakeholders will “freak-out” at seeing no greens, but I believe all projects are yellow until they are delivered.  We need to teach stakeholders that this a reality of doing business.  

Don't forget to leave your comments below.

Read 6713 times Last modified on Wednesday, 29 August 2012 10:52
Greg Smith

Greg Smith is a seasoned Agile coach and the founder of GS Solutions Group. He is a Certified Scrum Master, Certified Agile Project Manager, and a PMI Agile Certified Practitioner.

During his career Greg has held positions as a Product Manager, Program Manager, Development Manager, Scrum Master, and Project Manager.  He has received numerous awards for his work in helping start-ups establish good software practices, and for helping large enterprises overcome bureaucracy and deliver urgent projects.

Greg became an instructor for Agile Project Management at Bellevue College in 2005. 

In 2009 Greg co-authored Becoming Agile in an Imperfect World.  This book has helped a number of companies move to a more effective project management lifecycle, and is on the suggested reading list for the PMI Agile Certified Practitioner exam. 

Greg provides all type of agile training, including preparation for the PMI ACP exam. He also specializes in helping companies move to Agile. 

greg@gssolutionsgroup.com
www.gssolutionsgroup.com

Comments  

 
+1 # brent walker 2012-08-29 15:28
I agree with your premise and feel that we should be presenting status in some other terms besides R/Y/G. In the Agile world, why do we even use R/Y/G? Where do those indicators map to my stories? If my Product Owner has prioritized my backlog, which includes my risk items, then why isn't simply reporting on my project burn-up sufficient? I was recently convicted that I am not managing my risks well enough and am therefore the cause of any misunderstandin gs. If i accurately manage my risks and report on those risks then managment will see my overall risk values changing and being worked. As it is now, they have very little visibility into the risks I'm managing and use R/Y/G as the only way to understand when risk events occur. I agree that there needs to be a better way to report status but simply removing green and adding orange is really semantical. Could I just not state that Green means that there are inherent risks and they may or may not occur just like your Yellow definition?
Reply | Reply with quote | Quote
 
 
0 # Sean Ellis 2012-08-29 16:25
I tend to agree with Brent that replacing green with yellow is purely semantic. In my organisation we use vectors as well as the RAG rating to indicate where we expect the project to be heading based on the currently identified risks and issues which tends to add a little more context to the overall rating.
Reply | Reply with quote | Quote
 
 
0 # angie 2012-08-29 20:01
I agree it seems the color change of status is really semantics. However, this approach seems to target people's emotions and thoughts around statuses. It's a subtle enough of a change to foster a change in perception about a project and set people's expectation's differently. This could be a good tool to use when trying to change culture and slowly transition into a different way of reporting status.

I think the question to ask is how can we effectively report in a quick and easy way the things that are important regarding the timeline around a project. I don't know if there a single thing that can effectively convey that. It seems you need a combination of information to get that message across to people.
Reply | Reply with quote | Quote
 
 
0 # Upendra 2012-09-05 10:22
I too agree with you Greg. Nice explanation on how to address the stakeholder feelings and at the same time being transparent
Reply | Reply with quote | Quote
 
 
+1 # Majid 2012-09-05 13:26
I suggest instead of using three color to use 4 colors. Red, Yellow, Orange and Green.

Green: Project is in good shape and no risk at the moment
Yellow: (Warning for upcoming risks)The project does not have any known issues but there is still high risk that something could go wrong (as demonstrated by the cone of uncertainty). As with any project in flight, we are managing it cautiously and we are doing our best to deliver successfully.
Orange: (Risk identified with min damage. Can control the damage with proper measures in hand). An issue has surfaced and the project goals are in jeopardy. We are triaging the issue(s) and at this time we believe we can still be successful
Red: (Same) An issue has surfaced and we do not believe 100% project success can be obtained due to the discovery. More than likely we will either miss the desired date, or exceed budget, or not be able to deliver the desired scope by the target date.
Reply | Reply with quote | Quote
 
 
+1 # Bernard Plante 2012-09-06 15:00
No matter the colors, I think the important point is the signification you give to the colors used. My method consists of using standard G/Y/R statuses but for me Y and R not only means that something is going wrong but also points out the level of attention to give to the item in function of its importance in time.

Explainations.

For example, if an under control (green) item is near to deliver (in general two weeks before the delivery date), I change its status from greeen to yellow in order to point out that this particular item will deliver soon. If the item to deliver is a major component of the project, it can turn from green to red (meaning important delivery to come).

This way, stakeholders know that yellow or red do not automatically means "out of control" but can also mean "near to deliver".

From my experience, this way to manage the statuses keep the upper management more relax facing Y or R colors but another important effect is that it keeps them more aware of the progress of the project. It avoids having green items delivering without anyone noting... thinking that it was just normal and not seeing the work behind it.
Reply | Reply with quote | Quote
 
 
0 # Tom 2012-09-07 10:28
I see a couple of possible "options" here. What about matching the color with a point on the cone of uncertainty, e.g., Green with 25% confidence (large uncertainties remain), green with 90% confidence (almost all uncertainties have been removed)? The level of uncertainty could be tracked as a function of the overall percentage of the project which has been completed.

Another option is defining and using a color continuum, from red to green, perhaps, with defined interim shades (this one invites a certain level of ambiguity).

Another option is a "weather report", e.g., green with a 50% chance of yellow by next week. That way, you get out in front of possible issues, and you avoid the "how did this happen" question.

However you do it, it is critical that everyone know and accept what a specific color means.
Reply | Reply with quote | Quote
 
 
0 # Renu Sharma 2012-09-09 14:38
Any project is never free from risk and issues. That is why continuous risk management is part of project planning and control . Any project manager knows that where are we against the plan and whether going to meet the plan or not. Just on the basis of unknown the color should not be changed . As and when it is forseen that there is something that may hamper the plan the color should be changed. It is noticed that normally PM to hide the issue try to depict a green status , which is wrong. Analyse the project status and if there is a manageable or non manageable risk / issue share it with stakeholders honestly and mark the project color accordingly. An honest communication will not keep stakeholders in dark. Having 4 colors may depict the status in better way than getting away with green.
Reply | Reply with quote | Quote
 
 
0 # BillyBob 2013-05-01 15:01
The colors are only there to show a difference in item 1 from item 2 - pick any colours you want or as many as you want.

What is needed is communication on what the colours mean, then your visual communication tool (colour) will have a consitent meaning to the project team and stakeholders.
Reply | Reply with quote | Quote
 

Add comment